In the 1970s, Lengiprotrans prepared a project for electrical interlocking at Liiva station for 30 switches. A compressor station and a transformer substation were designed at the station.
The page shows the objects of the selected type, the design of which was performed in the selected period
950
projects completed
Site surveys for construction involve comprehensive investigations of natural environment of an area and/or a construction site.
Specialists of JSC Lengiprotrans design transport development master-plans, which includes activities associated with placement of all railway infrastructure facilities in accordance with the process solutions adopted. The design work includes environmental impact assessment and development of recommendations on environmental protection.
The page shows the objects of the selected type, the design of which was performed in the selected period
In the 1970s, Lengiprotrans developed a project to rewire the Pärnu - Mõisaküla narrow-gauge section to the 1520 mm wide gauge line with access to the Riga - Aloa - Myizaküla broad gauge line....
Photo: Siverskaya station (source: wikimedia.org)
The two-track railway line Skovorodino - Shimanovskaya belongs to the Trans-Baikal Railway and is part of the Trans-Siberian Railway. In 1970-1980, Lengiprotrans developed a project for...
The Siverskaya - Luga railway line is a section of the Varshavskaya line of the Oktyabrskaya railway.
The project of the second tracks on the section with electrification was developed by...
Leningrad Institute of Railway Transport Engineers named after Academician V.N. Obraztsova (LIIZhT, now the Emperor Alexander I St. Petersburg State Transport University, PGUPS) is a higher...
Pages