Specialists of JSC Lengiprotrans design transport development master-plans, which includes activities associated with placement of all railway infrastructure facilities in accordance with the process solutions adopted. The design work includes environmental impact assessment and development of recommendations on environmental protection.

The page shows the objects of the selected type, the design of which was performed in the selected period
  • 1980 — 1989
Электрификация участка Кокчетав – Новоишимская
Kokchetav (Kokshetau) - Novoishimskaya - a section of the former Tselinnaya railway. The site was electrified using a 2x25 kV AC system under the Lengiprotrans project in the 1980s.
  • 1980 — 1989
Соединительный путь Щербит — Кебир
For many years Lengiprotrans has been developing the railway network in the Syrian Arab Republic. The main task was to connect the seaports of Tartus and Latakia with the eastern regions of the...
  • 1980 — 1989
  • 1990 — 1999
Электрификация участка Беломорск — Сумский Посад
Railway line Belomorsk - Sumskiy Posad - section of the Oktyabrskaya railway. The line runs along the coast of the Onega Bay in the north-east of the Republic of Karelia. The line was...
  • 1990 — 1999
Пешеходный мост на пересечении улицы Мяэкалда с Октябрьским проспектом в Таллине
In the 1980s, Lengiprotrans developed a project for the construction of a pedestrian bridge at the intersection of Mäekalda Street with Oktyabrsky Avenue in Tallinn. Power supply was also designed...
  • 1980 — 1989
Железнодорожный путепровод на пересечении улиц Сютес и Тиркшлю в г. Мажейкяй
In the 1980s, Lengiprotrans engineers designed various projects in the Baltics. Thus, by order of the Baltic Railway, Lengiprotrans has developed a project for a railway overpass in the town of...
  • 1980 — 1989
  • 1990 — 1999
Реконструкция моста через реку Нарву
The reconstruction of the bridge over the Narva River in the Estonian city of Narva was carried out according to the Lengiprotrans project. Design and survey work began in 1985 when...